The PPEA allows receipt of unsolicited proposals for a qualifying project. The PPEA also allows solicited proposals. For purposes of outlining project delivery steps, a process initiated by an unsolicited proposal will have an additional step at the beginning. Accordingly, the below listed steps shall apply for any PPEA project.
- Unsolicited Proposal an Initiating Step
The PPEA permits the School Board to receive and evaluate unsolicited proposals from private entities to acquire, design, construct, improve, renovate, expand, equip, maintain, or operate a qualifying project. The School Board's general policy is to reserve acceptance of unsolicited proposals for cases of truly innovative ideas, because, in other cases, traditional procurement process are generally viewed as more likely to achieve full and open competition from the bidding community.
To be considered, one original and eleven (11) copies of any unsolicited proposal must be submitted to Executive Director, Facilities Services, 1568 Corporate Landing Parkway, Suite 200, Virginia Beach, VA 23454. While the School Board reserves the right to charge a review fee as permitted by the PPEA, fees are not required at this time. The unsolicited proposal shall take the form of a conceptual proposal and in a format consistent with the guidelines and supporting documentation.
The Superintendent, after consultation with the School Board, may accept an unsolicited proposal. If the Superintendent determines not to accept the proposal, the Superintendent will return the proposal, together with accompanying documentation, to the proposer. For an unsolicited proposal that purports to develop specific cost savings, the Superintendent shall specify the basis for the rejection in writing.
If the Superintendent accepts the proposal, the Superintendent shall proceed to post the proposal and publish the notice requesting competing proposals. Prior to posting, the Superintendent and the Office of the City Attorney (or other retained legal counsel) shall review any request to protect information in the proposal that the proposer sought to withhold form posting. The posting shall occur within ten (10) business days of the decision to accept the unsolicited proposal. The posting shall include a contact person to receive public input on the concept. Additionally, at least one copy of the unsolicited proposal will be made available for public inspection.
- Solicitation of Conceptual Proposals or Notice of Acceptance of Unsolicited Proposal
The School Board may solicit proposals for any qualifying project by means of a Solicited PPEA, which usually is initiated by a Request for Proposals (the “RFP”). Alternatively, if the Superintendent has accepted an unsolicited proposal, the Superintendent will publish a notice requesting competing proposals.
The notice or the RFP shall:
- Identify the qualifying project specifically or conceptually;
- Provide a deadline for the submission of competing proposals, which shall be at least 45 days from the notice or solicitation;
- Identify whether the proposals will be reviewed using procedures for competitive sealed bidding or competitive negotiation for nonprofessional services;
- Provide any other conditions for the submission of competing proposals;
- Provide additional information regarding the project, as needed, and to whom questions regarding the notice or solicitation may be directed.
The notice or RFP shall be posted on the VBCPS website and in a manner consistent with the posting of other VBCPS procurement solicitations. The costs of completion of such proposal shall be the sole responsibility of the proposer(s).
Contemporaneous with the notice or solicitation, the Superintendent shall document in writing the decision to proceed with either competitive sealed bidding or competitive negotiation as described by the VPPA. The use of competitive negotiation requires a determination, in writing, that doing so is likely to be advantageous to the Public Schools and the public based upon either: i) the probable scope, complexity or priority of the project; ii) the risk sharing including guaranteed cost or completion guarantees, added value or debt or equity investments proposed by the private entity; or iii) an increase in funding, dedicated revenue source or other economic benefit from the project would not otherwise be available.
- Conceptual Proposal Stage
Only proposals complying with the requirements of the PPEA and this Policy and supporting Guidelines and documents that contain sufficient information for a meaningful evaluation and that are provided in an appropriate format, as described below, will be considered by the Superintendent for further review at the conceptual stage. At least one copy of each of the proposals shall be made available for public inspection. A scan of the nonproprietary portions of the conceptual proposals will be posted on the VBCPS website within ten (10) business days of initiation of review. The posting shall include a contact person to receive public input on the concept.
After reviewing an unsolicited proposal and any competing proposals submitted, the Superintendent may determine:
- not to proceed further with any proposal,
- to proceed to the detailed phase of review one or more of the proposers, or
- to request modifications or amendments to any proposals.
However, the Superintendent may not proceed to the detailed phase with only one proposer unless it has determined in writing that only one proposer is qualified or that the only proposer to be considered is clearly more highly qualified than any other proposer.
- Detailed Proposal Stage
The decision to proceed to the detailed phase shall include sending a request for detailed proposals to the chosen proposers. The costs of completion of such proposal shall be the sole responsibility of the proposer(s).
If expressly approved by the School Board, the Superintendent may include a proposal payment in a fixed amount as an enticement for proposers to submit a detailed proposal. Such proposal payment would be paid to unsuccessful proposers that submit a detailed proposal, and the payment is conditioned upon VBCPS retaining the right to use technical solutions, design concepts, and any other proprietary information contained in the unsuccessful detailed proposal.
Unless otherwise provided in this request, the required components of a detailed proposal will be provided in the Guidelines and supporting documents. The complexity of the request will vary substantially depending on the nature of the project and whether the project includes financing, long-term operations, acquisition of real property, or other complicated components. The decision as to whether to use the financing plan contained in any proposal (whether solicited or unsolicited) is at the School Board's sole discretion.
If the project is principally the design and construction of a facility, the Superintendent may include the form contract utilized in other VBCPS projects.
Only detailed proposals complying with the request for detailed proposals will be considered by the Superintendent. The request for detailed proposals shall provide the method of evaluation, including specifying the factors that will be used in evaluated the proposals and whether numerical scoring will be used in evaluating the proposals.
- Agreement Negotiation Stage
If the review of the detailed proposals provides a preferred proposer, the Superintendent may begin negotiation of a comprehensive agreement. However, if there are work items required before a determination of the preferred proposer, the Superintendent may negotiate an Interim Agreement. The work items in an Interim Agreement include: project planning and development; design and engineering; environmental analysis and mitigation; survey; ascertainment of financing through financial and revenue analysis; establishment of a process and timing of the negotiation of a comprehensive agreement. Because of the required approvals and its tendency to limit competition, the use of an Interim Agreement is disfavored.
The PPEA legislation includes items provided for in a comprehensive agreement in §56-575.9. This list is reproduced in the Guidelines.
Once an interim or comprehensive agreement’s material terms have been identified and agreed to in principal between VBCPS and the private entity, the Superintendent shall brief the School Board and provide a recommendation. Using this briefing, the posted conceptual proposals, and any other relevant materials, the School Board shall schedule a public hearing to receive input regarding the proposed project. This public hearing must be at least thirty (30) days prior to any vote to execute either an interim or comprehensive agreement.
After an interim or comprehensive agreement has been negotiated in substantially completed form, a copy of the agreement shall be posted on the VBCPS website. This posting of the agreement should occur at least thirty (30) days prior to any vote to execute the agreement. The posting shall include a contact person for submission of public input. The public input shall be gathered and transmitted to the School Board prior to the requested action to approval an interim or comprehensive agreement.
- Required Approvals
After the briefing of the School Board regarding the material terms of an interim or comprehensive agreement, the Superintendent shall request that the City Council take action to approve the proposed interim or comprehensive agreement.
Upon receipt of the City Council approval, the Superintendent shall request the School Board authorize the execution of the interim or comprehensive agreement. The scheduling of this action shall be after the required public hearing and any posting requirements have been completed. An example of the form of an authorizing resolution is provided in the Guidelines and supporting documentation.
As required by Virginia Code § 56-575.9 (F), as amended, when the School Board enters into an agreement pursuant to the PPEA, a copy should be submitted to the Auditor of Public Accounts within thirty (30) days.