Princess Anne Middle School Replacement

Princess Anne Middle - Replacement

Princess Anne Middle

Milestones

  • Original Building Opened: 1974
  • Existing Building Demolition: Summer/Fall 2017
  • Groundbreaking: October 11, 2018
  • Construction Start Date: 2018
  • Projected Completion: 2021

Building Facts

  • Current Building Capacity: 1,500
  • Current Student Membership: 1,479
  • New Building Size: 257,784 sq. ft.
  • Total CIP Project Cost: $78.9 million
  • Architect: RRMM Architects
  • Demolition Contractor: R. J. Smith Construction Inc.
  • General Contractor: McKenzie Construction Corporation

Additional Info:

Project Facts:

  • The replacement of Princess Anne Middle School is funded in the 2016/17 Capital Improvement Program adopted by City Council in May 2016.
  • The School Board voted to award a demolition contract to R. J. Smith Construction Inc., on August 1, 2017, in the amount of $954,650.
  • A presentation on the design for the new School was made to the School Board on October 24, 2017
  • The School Board on August 14, 2018 authorized the execution of a construction contract in the amount of $63,729,000 with McKenzie Construction Corporation.