Completed New Building - Linkhorn Park Elementary School

Linkhorn Park ES Original Building Opened
January 1955
Groundbreaking
March 12, 1997
Construction Start Date
March 1997
Renovation Completed
January 1998
Building Dedicated
December 7, 1999

Building Facts

Student Capacity: 716
Building Size: 76,285 sq. ft.
Project Cost: $6.8 million
Architect: Shriver & Holland Associates
Contractor: S. B. Ballard Construction Company

Construction Highlights

  • Linkhorn Park  Elementary is a prototype plan used by the school division for 13 other elementary schools to include: Christopher Farms, Arrowhead, Seatack, New Castle, Bayside, Kempsville Meadows, Woodstock, Hermitage, Three Oaks, Brookwood, Windsor Woods, Newtown and Elementary School 2007-2008.
  • This “community” school is organized as a square floor plan with three clustered classroom wings housing 30 general classrooms, special education classrooms, teacher’s workrooms and various service facilities. 
  • Separate entry points for teacher/parent access, students (buses) and service functions have been situated in order to maintain security and separation from vehicular traffic as well as to secure portions of the building that are not being  utilized for after school or off-hour functions.
  • Media center with seating for 50: 10,000 volume capacity; and 8 computer stations.
  • Cafetorium seating 270 and platform.
  • Faculty workrooms with work spaces, resource rooms, and restrooms.
  • Exterior Courtyard for outdoor education functions.
  • Commons area for indoor gatherings.
  • Technology features include a computer lab and head-end equipment room features.