Original Building Opened
Fall 2001 |
Addition Start Date
December 2005 |
Construction Completion
January 2007 |
Addition Dedicated
May 2, 2007 |
December 1, 2006 |
|
Building Facts
| Student Capacity (with addition): |
2,181 |
| Building Size (with addition): |
308,924 sq. ft. |
| Project Cost: |
$7,865,619 |
| Architect: |
Dills Ainscough Duff Architects |
| Contractor: |
Blueridge General, Inc. |
Building Improvements
- Construction of a twenty-classroom addition
- For a seamless transition the new addition matches the existing construction
- Addition improved student flow throughout the facility
- Improved instructional technology within the addition classrooms, as well as in the renovated areas inside the existing building.
- This project also included an amphitheatre and an entrance canopy.
- Both the design and construction (total project delivery) was completed in less than two years.
|
|
|
|
|
|