Completed New Building - Brookwood Elementary School
| Original Building Opened 1968 |
|
| Groundbreaking June 5, 2006 |
|
| Construction Start Date July 3, 2006 |
|
| Projected Completion Date October 5, 2007 |
|
| Building Dedicated May 7, 2008 |
Building Facts
| Student Capacity: | 590 |
| Building Size: | 78,721 sq. ft. |
| Project Cost: | $16.5 million |
| Architect: | Waller, Todd, and Sadler |
| Contractor: | McKenzie Construction Corporation |
Building Improvements
The school and staff were temporarily located behind Plaza Elementary in portable classrooms while the new facility was constructed. Classes were held in portable classrooms during the 2006-2007 school year and 2 months of the 2007-2008 school year to allow time to demolish the existing building and complete the new.
Spaces within the school include:
- General classrooms
- Administrative offices
- Clinic
- Guidance suite
- Music rooms
- Art room
- Media center
- Special education classrooms
- Cafetorium with platform
- Gymnasium
- Faculty dining
Site improvements include:
- Student/staff parking
- Bus loop
- Athletic fields
- Play areas and landscaping