- Original Building Opened: Fall 2001
- Addition Start Date: December 2005
- Construction Completion: January 2007
- Addition Dedicated: May 2, 2007
Building Facts
Student Capacity (with addition): 2,181
Building Size (with addition): 308,924 sq. ft.
Project Cost: $7,865,619
Architect: Dills Ainscough Duff Architects
Contractor: Blueridge General, Inc.
Building Improvements
- Construction of a twenty-classroom addition
- For a seamless transition the new addition matches the existing construction
- Addition improved student flow throughout the facility
- Improved instructional technology within the addition classrooms, as well as in the renovated areas inside the existing building.
- This project also included an amphitheatre and an entrance canopy.
- Both the design and construction (total project delivery) was completed in less than two years.